![]() Project removes the leading work value with 0 value. ![]() NOTE: In Microsoft Office Project 2007 and earlier versions, click Task Usage on the View menu.Ĭlick to select the value 0 at the beginning of the task's work values under the timescale (the row labeled "Work" in the right pane), and press DELETE. If a resource is assigned to the task, follow these steps: If no resources are assigned to the task, change the duration to zero, and then change the duration back to the original value. To remove a split at the beginning of a task, use the method appropriate for your situation: However, this method does not work if the split is assigned at the beginning of a task (a leading split). If you drag a portion of a split task so that it touches another portion, Microsoft Project removes the split. In Microsoft Project, you can split a task so that the task is interrupted, and then resumes later in the schedule.